According to Asia News PIME aisanews, the Colombo East Container Terminal (ECT) in Sri Lanka has been shut down, with four out of five tenders for cross loading trucks cancelled and only some cranes put into use.It is expected that by 2027, the losses will reach as high as $126.7 million.
The Colombo Port East Container Terminal covers an area of approximately 75 hectares and is operated byThe Sri Lanka Ports Authority fully owns and is responsible for the development of the terminal. The first phase of the dock project was completed in mid-2015,The coastline is 450 meters long and the water depth is 18 meters, which can accommodate 18000 TEU containers for docking. However, due to the cancellation of four consecutive tenders for the Phase II dock project, it has still not been put into operation as expectedCurrently, the Sri Lankan government is making its fifth attempt to purchase 15 cross transport vehicles.
Although the civil engineering has been completed by about 82% to 85%, the dock still needs to wait for at least 10 to 12 months before the equipment can be delivered to the site. The reason for this situation is that the terminal procurement process has repeatedly encountered problems. Since 2021, Colombo Port East Container Terminal has issued five tenders for cranes, of which four tender procedures have been cancelled. The relevant personnel explained, "In the third bidding, the winning bid approved by the cabinet was suspended within a few weeks, reportedly due to receiving specific instructions. Subsequently, after the unsuccessful bidder filed a legal lawsuit, the winning bid was completely invalidated
According to senior port officials, "12 ship shore cranes (STS) and 40 automated gantry cranes (ARMG) have been delivered. However, four STS cranes have not yet been put into use, and only 14 ARMG cranes are in operation. It is reported that the entire fleet of ARMG cranes is in a state of disuse. A test conducted at that time showed that the loading and unloading capacity of each crane was only 7.8 times per hour. The World Bank's benchmark indicator for port performance suggests that this value should exceed 20 times.
Due to the terminal not being ready yet, these cranes have been placed in other locations within the port area, and some of the equipment has been temporarily put into use. They pointed out, "Therefore, these devices must now be relocated and reassembled on designated tracks - a cost that was never included in the budget before. This not only poses a risk of equipment damage (such as possible deviations in automation components), but may also lead to disputes with suppliers regarding defect liability attribution
According to Ranga Malalasekara and Udaya Kamaladasa, former directors of the Sri Lanka Ports Authority, "The total estimated cost for the two stages of the terminal is $755 million, of which $550 million has been spent by early 2026, with significant amounts still to be paid. This cost covers civil engineering, cross harbour vehicles (not yet contracted for procurement), various equipment, terminal operating systems, and operating buildings
A committee composed of senior officials from the Sri Lanka Ports Authority estimates that if the cross loading vehicles are not in place, the revenue loss of Colombo Port East Container Terminal in 2026 will be between 28.2 million and 105.6 million US dollars, while the loss in 2027 may reach as high as 126.7 million US dollars.